The life of a project

Purchases and expenses

How do I request a service or a subcontract for the project?Like the material request, but with the budget's service-type resources.

Where BIM › Inventory › Service Request › Service Request

Before you start

For the Purchase Requisition app's own menu, the Request Services Menu profile.

How do I request a service or a subcontract for the project?

Steps

  1. Click New, choose the Project and the dates.
  2. Click Load Services, choose the Service Type (Own Services, Sub-Contract or All) and tick the Budgets.
  3. If you turn on Separate in the request, one line per item is created and only with the resources marked as Sub Contract in the budget.
  4. Review the lines, the Supplier and the Cost, and click Approve.
  5. Click Purchase, assign a vendor per line and click Process to create the order.
  6. When nothing is left to order, click Finish.
Warning

If the request does not have Allow to Buy More, loading services deletes any lines already there.

A cancelled service request has no button to go back to New: create another.

Site note

Export XLS downloads the lines with concept, quantity, cost and subtotal.

From the project record, the Service Request button opens that project's requests.

Documented version: BIM 2.0 (base_bim_2 20.0.19.04.2026) · Odoo 20