Search for what you want to do and follow the steps. Each process shows where it is in the menu, what you need first and which mistakes to avoid.

The life of a project

Scheduling and progress tracking

How do I see the critical path and the float of each item?Items with no float form the critical path: any delay in them delays the end of the project.

Where Budget › Gantt button

How do I see the critical path and the float of each item?

Steps

  1. Open the budget's Gantt.
  2. Look at the Float column: working days the item can slip without delaying the finish. Critical items are in red.
  3. With Critical path on, their bars are painted red.
  4. Click Critical only to see only those items and their chapters.
Warning

Negative float (bright red) means a deadline or a constraint is not met: check the item.

Site note

Float is also on the item form (Total Float (d) and Critical) and in the item search with the Critical path and Negative float filters.

Finished items stop being critical.