How do I remove over-allocations by moving items automatically?Levelling delays items, as in MS Project, so that no resource goes over its capacity.

Where Gantt › Resources › Level resources · Budget › Scheduling tab › Level resources

Before you start

The resources need Max. units (capacity) and the project must be scheduled.

How do I remove over-allocations by moving items automatically?

Steps

  1. Open Resources from the Gantt and check in Over-allocations which resources go over their capacity.
  2. Leave Only within float ticked so the end of the project does not move, or untick it if it can slip.
  3. Click Level resources and confirm.
  4. Items are placed in order of start, critical ones first, on the first day their resources fit. The message tells you how many moved and how many over-allocations are left.
Warning

Levelling saves the schedule: it cannot be undone from the histogram. Save a baseline first if you want to compare.

Started items and items pinned with Must start on or Must finish on do not move: their over-allocations remain.

Site note

With Include other projects ticked, levelling takes into account what those resources do in other budgets.

Documented version: BIM 2.0 (base_bim_2 20.0.19.04.2026) · Odoo 20