Search for what you want to do and follow the steps. Each process shows where it is in the menu, what you need first and which mistakes to avoid.

The life of a project

Scheduling and progress tracking

How do I make successors move by themselves when an item changes?With automatic scheduling, changing an item in its form, with UPD or by importing reschedules its successors.

Where Budget › ST tab › Automatic Scheduling

How do I make successors move by themselves when an item changes?

Steps

  1. In the budget's ST tab turn on Automatic Scheduling.
  2. Change the dates, duration, a constraint or the predecessors of an item from its form and save.
  3. On saving, its successors move to respect the links, and floats and the critical path are recalculated.
Warning

It comes turned off so that existing projects do not move by themselves.

Site note

In the Gantt successors always move, whether it is on or off.

It reschedules only once per save, even if many items change at the same time (for example with UPD or an import).

Documented version: BIM 2.0 (base_bim_2 20.0.19.04.2026) · Odoo 20