The life of a project

Maintenance

How do I create and carry out a maintenance work order?The task with owner, timer, review and signature.

Where BIM › Maintenance › Home › Tasks

Before you start

BIM Maintenance profile.

How do I create and carry out a maintenance work order?

Steps

  1. Go to BIM › Maintenance › Home › Tasks and click New (or create the task from the plan or from a request).
  2. Enter the Name and choose Type Task, Task Plan, Category 1, Priority, Estimated Duration (minutes) and the Responsible.
  3. Click To Process.
  4. When you start, click Play and when you finish Stop: Begin Date, End date and Real Duration (minutes) are filled in.
  5. Complete the subtasks, note the resources and the Downtime (minutes), and click To Review.
  6. Choose Who Review, collect the signature on the Signature tab and click To finished.
Warning

Without a Responsible it does not move to process, and without Who Review it cannot be finished: "You must select a contact".

It does not move to review if any Required subtask is unfinished: "You must complete all required subtasks".

The Real Duration counts from the first Play to the last Stop: intermediate pauses also count.

A finished task is locked; To Draft reopens it.

Site note

The task's Cost is the sum of its resources.

If the task comes from a request, the request changes state at the same time as the task.

Documented version: BIM 2.0 (base_bim_2 20.0.19.04.2026) · Odoo 20