How do I import a BC3 budget?Bring in a budget made in another program (FIEBDC-3 format).

Where BIM › INT › Budget Importer › Importation job

How do I import a BC3 budget?

Steps

  1. Go to INT › Budget Importer › Importation job.
  2. Click New.
  3. Choose the Version (BC3, Excel template, Project XML...) and the destination Project.
  4. Check Create non-existent products to register the new resources.
  5. Upload the file and click Import.
  6. Check the total against that of the source program and click UPD.
Warning

The extension must be lowercase: .bc3. A .BC3 file is rejected; rename it first.

Site note

If you do not see the finished import, remove the To execute filter.