The life of a project

Scheduling and progress tracking

How do I see whether a resource is over-allocated?The load of each resource per day, week or month against its capacity, also across projects.

Where Gantt › Resources button · Budget › Scheduling tab › Resources

How do I see whether a resource is over-allocated?

Steps

  1. In the Gantt click Resources.
  2. In the list on the left type in Max. units how many people or machines of that resource can work at the same time. It is saved on the product.
  3. Choose a resource: the chart shows its load, the capacity line and, in red, the over-allocated periods.
  4. Tick Include other projects to add what the resource has in other budgets on the same dates.
  5. Over-allocations lists the dates and the items involved, and Resource usage is the table of all resources per period.
Site note

To remove over-allocations automatically, use Level resources.

Daily capacity is Max. units × the company's working day. With 0 there is no limit.

To solve an over-allocation, move one of the items with float in the Gantt or reduce its crew.

Documented version: BIM 2.0 (base_bim_2 20.0.19.04.2026) · Odoo 20