BIM 2.0Odoo 20

Process manual

Search for what you want to do and follow the steps. Each process shows where it is in the menu, what you need first and which mistakes to avoid.

The life of a project

Scheduling and progress tracking

How do I schedule an item that counts weekends and holidays, such as concrete curing?With an elapsed duration, the item counts every calendar day.

Where Item › Elapsed Duration

How do I schedule an item that counts weekends and holidays, such as concrete curing?

Steps

  1. Open the item and tick Elapsed Duration.
  2. Type its Duration in calendar days (for example, 7 days of curing).
  3. Save: the finish counts Saturdays, Sundays and holidays, and the successor can start on Monday.
Site note

For a wait between two items without creating a new item, use a lag in elapsed days on the link (`+7ed`).

In the Gantt an elapsed duration is shown in italics.

Documented version: BIM 2.0 (base_bim_2 20.0.19.04.2026) · Odoo 20