How do I certify from captures or measurement lines?Fill in CurQty with what was measured instead of typing it item by item.

Where BIM › Home › Certifications › Certifications › Measurements tab

Before you start

Bim Certification profile. Measurement captures in Finished, if you use them.

How do I certify from captures or measurement lines?

Steps

  1. Create the certification and, before loading it, open the Measurements tab.
  2. In Measurements Capture choose one or more finished captures of the project that have not been certified yet. The items from those captures are added to Only Concepts.
  3. Click Load: the CurQty of each item takes the sum of the quantities from the captures.
  4. If you prefer to measure inside the certification, turn on Use Measurements before Load: measurement lines (Quantity, Length, Width, Height) are created for the items that have measurements in the budget.
  5. Fill in the lines and click Insert measurement: CurQty becomes the sum of their Subtotal.
  6. Continue as usual: Validate and Certify.
Warning

If you send the certification back to draft, the captures are freed to be used in another certification.