How do I register a project measurement capture?Note what was measured on each item, by hand or from Excel, to certify it later.

Where BIM › Home › Certifications › Measurement Capture

How do I register a project measurement capture?

Steps

  1. First create the origins in Home › Certifications › Measurement Origin (e.g. site visit or customer request): Name and Description are enough.
  2. In Measurement Capture click New and fill in Measurement Origin (mandatory), Project, Budget and, if you wish, Stage, Date, Customer and Origin.
  3. Click the Load button with the + icon: it brings all the budget items with Qty Budget, Qty Last and Price Unit.
  4. If you prefer to add only some items, create them by hand in List and click the other Load button to complete their quantities and prices.
  5. You can also upload an Excel in File and click Import: column A the item's BIM ID, column B the quantity, with a header row.
  6. Type the period Qty or the accumulated Qty Origin (it calculates the period one and the Qty Accumulated).
  7. Click To Done. The capture stays in Done and ready to certify.
Warning

It does not let you finish if a Qty Origin exceeds the Qty Budget, or if all quantities are zero ("Debe introducir al menos una cantidad").

If the project has a Closing Expenses closed with a date equal to or later than the capture Date, it does not let you finish it.

Site note

Clear deletes all the lines; To Draft lets you edit again.

Finished captures feed the Executed column of the billing milestones.