How do I load a crew as the resources of an item?Insert at once the resources of a resource template (crew) into an item.

Where Item › PR button

Before you start

A crew created in Execution › Programming › Resource Template.

How do I load a crew as the resources of an item?

Steps

  1. In the crew, Resources tab, show the optional columns Resourse Type and Quantity and check each line.
  2. Open the item in the budget and click PR.
  3. Choose the crew in Resource Template and click Insert: one resource is created per line, linked to its product and with its unit, its quantity and the product's Cost.
  4. Click UPD in the budget.
Warning

Lines without an employee come in as Labor by default: change their Resourse Type if they are materials or equipment.

Site note

Equipment lines come in as an EQUIPOS resource and Administrative lines as FUNCIÓN / ADMINISTRATIVO.

In the budget header you can note the planned crews in the Resource Template field.