Search for what you want to do and follow the steps. Each process shows where it is in the menu, what you need first and which mistakes to avoid.

The life of a project

Machinery and tools

How do I record tool rental for a project?Daily tool rental, with its cost on the project and automatic handover to the person in charge.

Where BIM › Equipment › Rents › Tool rent

Before you start

Products with the Tool box ticked.

How do I record tool rental for a project?

Steps

  1. Go to Equipment › Rents › Tool rent and click New.
  2. Choose Contact, Date From:, Date To: and Project (and if you want Budget and Concept).
  3. In the Rented tools tab add each Tool: the Quantity is the days between the dates (minimum 1) and the Price Unit is its sale price.
  4. Click Action Rent: it moves to Rented and the project amounts are recalculated.
  5. When they are returned, click Action Finished.
Warning

Without dates, choosing a tool warns “Select dates to continue!”.

Changing dates or contact recalculates the quantity and price of all lines.

Site note

If the Contact is an employee's (their user), a tools delivery in their name is also created and validated.

From an Approved material request, the Tool Rent button creates the rental with its tools; tick Separate tools for one rental per tool.

The cost adds to the project as Tools rent while it is Rented or Finished.

Documented version: BIM 2.0 (base_bim_2 20.0.19.04.2026) · Odoo 20