Search for what you want to do and follow the steps. Each process shows where it is in the menu, what you need first and which mistakes to avoid.

The life of a project

Scheduling and progress tracking

How do I update progress to the status date and reschedule the remaining work?As in MS Project: mark what should be done and move what is pending after the status date.

Where Budget › Scheduling tab

How do I update progress to the status date and reschedule the remaining work?

Steps

  1. In the budget's Scheduling tab set the Status Date: the day up to which you report progress.
  2. Click Update as scheduled: what should have started before that date is marked as started and what should have finished, as finished. It never lowers progress already entered.
  3. In the Gantt or in Variance, correct the items that are behind.
  4. Click Reschedule pending work: what has not started does not start before the status date, and started items are extended by what they have left.
Site note

Update as scheduled also saves the earned value snapshot at that date.

The Gantt draws the status date as a dashed blue line.

Documented version: BIM 2.0 (base_bim_2 20.0.19.04.2026) · Odoo 20