Where Item › Elapsed Duration

Steps
- Open the item and tick Elapsed Duration.
- Type its Duration in calendar days (for example, 7 days of curing).
- Save: the finish counts Saturdays, Sundays and holidays, and the successor can start on Monday.
Site note
For a wait between two items without creating a new item, use a lag in elapsed days on the link (`+7ed`).
In the Gantt an elapsed duration is shown in italics.