How do I see a project's labor cost?Attendance, hour allocations and subcontractors are added up in the project's costs tab.

Where Project › Project Cost tab

Before you start

BIM Manager profile or See project costs.

How do I see a project's labor cost?

Steps

  1. Open the project and click UPD (or Update Project Cost inside the Project Cost tab).
  2. In Project Cost look at the lines by Type: Attendance, Labor (Allocation), Partner Attendance and Project Report.
  3. In the Costs block of the record compare MH Budget (hours of the items) with MH Actual (hours from attendance).
  4. For detail, use the project's Attendance, Timesheets and P. Attendance buttons.
Warning

Attendance and allocations are added separately: if you record the same hours both ways, the cost comes out doubled. Choose one per project.

The figures do not update by themselves: click UPD before reviewing them.

Site note

Attendance adds up the employees' attendance with Include For Bim; Labor (Allocation), the non-cancelled allocations; Partner Attendance, the subcontractor ones with Include in BIM.